Impact Air Quality Monitoring Results 
1-hour TSP Monitoring Results at Station AM1A
(Fan Sin Temple, 3 Sheung Wun Yiu G/F)
Date Start 1st Hour 2nd Hour 3rd Hour
Time Conc. Conc. Conc.
(hh:mm) (µg/m3) (µg/m3) (µg/m3)
12-Sep-11 13:26 82.1 80.6 79.6
1-hour TSP Monitoring Results at Station AM2
(12 Shan Tong New Village G/F)
Date Start 1st Hour 2nd Hour 3rd Hour
Time Conc. Conc. Conc.
(hh:mm) (µg/m3) (µg/m3) (µg/m3)
12-Sep-11 10:00 82.9 78.7 76.2
1-hour TSP Monitoring Results at Station AM3
(Roof of Switch Room at Riverain Bayside)
Date Start 1st Hour 2nd Hour 3rd Hour
Time Conc. Conc. Conc.
(hh:mm) (µg/m3) (µg/m3) (µg/m3)
12-Sep-11 10:12 75.3 80.3 81.4
1-hour TSP Monitoring Results at Station AM4A
(Roof of Switch Room at 168 Shek Kwu Lung Village)
Date Start 1st Hour 2nd Hour 3rd Hour
Time Conc. Conc. Conc.
(hh:mm) (µg/m3) (µg/m3) (µg/m3)
12-Sep-11 13:40 73.7 74.6 77.2