Location : NM1 (Tai Kwong Secondary School Rooftop - Façade)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A) Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq L10 L90
11-Jun-10 11:05 64.6 66.2 61.7 64.2 54.0 70 N
17-Jun-10 13:30 65.0 67.5 62.0 64.2 57.3 70 N
23-Jun-10 13:05 64.6 66.9 63.1 64.2 54.0 70 N
29-Jun-10 13:35 64.4 67.0 63.0 64.2 50.9 70 N
Location : NM2 (38 Ha Wun Yiu G/F - Free Field)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A)* Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq* L10* L90*
11-Jun-10 13:35 65.2 68.0 62.5 68.1 - 75 N
17-Jun-10 10:15 67.5 69.8 65.0 68.1 - 75 N
23-Jun-10 10:10 67.0 69.5 64.0 68.1 - 75 N
29-Jun-10 10:25 66.7 70.0 64.0 68.1 - 75 N
Location : NM3 (Wong Shiu Chi Middle School Rooftop - Façade)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A) Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq L10 L90
11-Jun-10 14:25 68.1 69.6 64.4 64.8 65.4 70 N
17-Jun-10 11:35 64.8 67.0 60.0 64.8 - 70 N
23-Jun-10 11:30 64.3 66.5 62.0 64.8 - 70 N
29-Jun-10 14:25 64.7 68.0 63.0 64.8 - 70 N
Location : NM4 (Uptown Plaza Block 4 Rooftop - Façade)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A) Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq L10 L90
11-Jun-10 14:20 67.9 69.0 66.5 67.4 58.3 75 N
17-Jun-10 11:05 68.0 71.0 65.0 67.4 59.1 75 N
23-Jun-10 13:30 67.8 71.5 64.5 67.4 57.2 75 N
29-Jun-10 13:00 68.1 71.5 65.0 67.4 59.8 75 N
Location : NM5 (The Paragon Clubhouse Rooftop - Façade)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A) Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq L10 L90
11-Jun-10 10:00 65.7 67.3 61.5 65.2 56.1 75 N
17-Jun-10 14:15 63.3 65.0 62.0 65.2 - 75 N
23-Jun-10 14:10 64.3 66.5 62.0 65.2 - 75 N
29-Jun-10 11:00 64.3 67.0 63.0 65.2 - 75 N
Location : NM6 (PLK Tin Ka Ping Primary School near the entrance - Free Field)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A)* Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq* L10* L90*
11-Jun-10 10:50 65.2 67.2 63.4 64.5 56.9 70 N
17-Jun-10 10:55 64.5 65.2 61.5 64.5 - 70 N
23-Jun-10 10:55 64.7 67.0 62.5 64.5 51.2 70 N
29-Jun-10 11:30 64.1 66.5 61.0 64.5 - 70 N
Location : NM7 (Riverain Bayside Switch Room Rooftop - Façade)
Day time 07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results
  Measured Noise Level for 30-min, dB(A) Baseline Noise Level, dB(A) Calculated Construction Noise Level, dB(A) ** Limit Level, dB(A) Exceedance (Y/N)
Date Start Time Leq L10 L90
11-Jun-10 9:45 61.8 63.3 57.7 61.5 50.0 75 N
17-Jun-10 9:35 58.9 60.5 56.0 61.5 - 75 N
23-Jun-10 9:50 60.1 61.5 56.5 61.5 - 75 N
29-Jun-10 9:50 59.8 61.0 57.0 61.5 - 75 N
Remarks
*  +3dB(A) Façade effect correction included
** Construction noise level is only calculated when Measured noise level (Leq) > Baseline noise level