Location : NM1A (168 Shek Kwu Lung
Village G/F - Façade) |
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A) |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A) |
Exceedance (Y/N) |
Date |
Start Time |
Leq |
L10 |
L90 |
6-Jun-13 |
10:44 |
63.6 |
65.0 |
60.5 |
64.2 |
63.6 |
75 |
N |
11-Jun-13 |
10:28 |
64.5 |
66.0 |
60.5 |
64.2 |
75.0 |
75 |
N |
17-Jun-13 |
11:05 |
62.3 |
63.9 |
60.0 |
64.2 |
62.3 |
75 |
N |
28-Jun-13 |
10:48 |
61.5 |
62.5 |
58.5 |
64.2 |
61.5 |
75 |
N |
|
|
|
|
|
|
|
|
|
Location : NM2
(38 Ha Wun Yiu G/F - Free Field) |
|
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A)* |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A) |
Exceedance (Y/N) |
Date |
Start Time |
Leq* |
L10* |
L90* |
6-Jun-13 |
11:24 |
66.9 |
68.6 |
63.8 |
68.1 |
66.9 |
75 |
N |
11-Jun-13 |
11:20 |
66.0 |
67.5 |
62.5 |
68.1 |
66.0 |
75 |
N |
17-Jun-13 |
10:15 |
65.1 |
66.0 |
63.0 |
68.1 |
65.1 |
75 |
N |
28-Jun-13 |
13:20 |
67.2 |
69.0 |
65.0 |
68.1 |
67.2 |
75 |
N |
|
|
|
|
|
|
|
|
|
Location : NM3
(Wong Shiu Chi Middle School Rooftop - Façade) |
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A) |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A)# |
Exceedance (Y/N) |
Date |
Start Time |
Leq |
L10 |
L90 |
6-Jun-13 |
14:28 |
65.6 |
67.0 |
63.0 |
64.8 |
70.0 |
70 |
Y |
11-Jun-13 |
10:40 |
67.1 |
68.3 |
65.9 |
64.8 |
70.0 |
65 |
Y |
17-Jun-13 |
13:50 |
65.3 |
66.5 |
64.0 |
64.8 |
70.0 |
65 |
Y |
28-Jun-13 |
11:17 |
65.2 |
66.9 |
63.8 |
64.8 |
70.0 |
70 |
N |
|
|
|
|
|
|
|
|
|
Location : NM4
(Uptown Plaza Block 4 Rooftop - Façade) |
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A) |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A) |
Exceedance (Y/N) |
Date |
Start Time |
Leq |
L10 |
L90 |
6-Jun-13 |
13:25 |
63.6 |
65.0 |
61.0 |
67.4 |
63.6 |
75 |
N |
11-Jun-13 |
10:00 |
65.4 |
66.7 |
64.2 |
67.4 |
65.4 |
75 |
N |
17-Jun-13 |
13:05 |
64.4 |
65.5 |
63.0 |
67.4 |
64.4 |
75 |
N |
28-Jun-13 |
10:26 |
63.9 |
66.0 |
62.1 |
67.4 |
63.9 |
75 |
N |
|
|
|
|
|
|
|
|
|
Location : NM5
(The Paragon Clubhouse Rooftop - Façade) |
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A) |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A) |
Exceedance (Y/N) |
Date |
Start Time |
Leq |
L10 |
L90 |
6-Jun-13 |
13:12 |
66.2 |
67.9 |
63.9 |
65.2 |
75.0 |
75 |
N |
11-Jun-13 |
13:20 |
62.5 |
64.5 |
59.0 |
65.2 |
62.5 |
75 |
N |
17-Jun-13 |
13:20 |
62.9 |
63.5 |
61.5 |
65.2 |
62.9 |
75 |
N |
28-Jun-13 |
14:04 |
67.3 |
68.9 |
65.1 |
65.2 |
75.0 |
75 |
N |
|
|
|
|
|
|
|
|
|
Location : NM6
(PLK Tin Ka Ping Primary School near the entrance - Free Field) |
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A)* |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A)# |
Exceedance (Y/N) |
Date |
Start Time |
Leq* |
L10* |
L90* |
6-Jun-13 |
11:28 |
56.5 |
58.0 |
53.5 |
64.5 |
56.5 |
70 |
N |
11-Jun-13 |
13:15 |
62.0 |
64.0 |
58.5 |
64.5 |
62.0 |
65 |
N |
17-Jun-13 |
11:30 |
64.8 |
66.0 |
63.5 |
64.5 |
70.0 |
70 |
N |
28-Jun-13 |
13:13 |
61.7 |
63.2 |
59.6 |
64.5 |
61.7 |
70 |
N |
|
|
|
|
|
|
|
|
|
Location : NM7
(Riverain Bayside Switch Room Rooftop - Façade) |
|
|
|
|
|
Day time
07:00-19:00 hrs Normal Weekdays Impact Noise Monitoring Results |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Measured Noise Level for 30-min, dB(A) |
Baseline Noise Level, dB(A) |
Corrected Construction Noise Level, dB(A) ** |
Limit Level, dB(A) |
Exceedance (Y/N) |
Date |
Start Time |
Leq |
L10 |
L90 |
6-Jun-13 |
10:32 |
57.8 |
59.4 |
54.9 |
61.5 |
57.8 |
75 |
N |
11-Jun-13 |
11:05 |
62.0 |
63.5 |
58.5 |
61.5 |
75.0 |
75 |
N |
17-Jun-13 |
9:55 |
57.7 |
60.0 |
55.9 |
61.5 |
57.7 |
75 |
N |
28-Jun-13 |
14:15 |
60.8 |
62.0 |
57.0 |
61.5 |
60.8 |
75 |
N |
|
|
|
|
|
|
|
|
|
Remarks |
|
|
|
|
|
|
|
|
* +3dB(A) Façade effect correction included |
|
|
|
|
|
|
# - Limit Level
of 70dB(A) applies to education institutes while 65dB(A) applies during
school examination period. |
|
|
** Construction
noise level is only calculated when Measured noise level (Leq) > Impact
noise level. |
|
|
|
If Measured noise level < Impact noise
level, Corrected noise level = Measured noise level |
|
|
|
|
|
|
|
|
|
|
|
|