Site
Inspection Summary
Contract No. |
HY/2012/06 |
Date: |
8 May 2014 |
Time: |
14:00 |
Inspection No.: |
24 |
|
Nil |
|
|
|
Follow-up
Observations |
1. |
Mud trails were
cleared (Closed). |
|
|
|
New
Observations |
|
Nil. |
|
Reminders |
2. |
The Contractor was
reminded to provide effective dust suppression measures to stockpiles of
filling materials at Area 346. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
13 May 2014 |
Time: |
14:00 |
Inspection No.: |
25 |
|
Nil |
|
|
|
Follow-up
Observations |
|
Nil. |
|
|
|
New
Observations |
1. |
Muddy water was
observed outside the construction site. The Contractor was reminded to clear
the muddy water on the public road and review measures to prevent silt from
entering the drainage systems and public area. |
2. |
Chemical containers were observed without the
provision of drip tray. The Contractor was reminded to provide drip trays to
chemicals or remove them. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
20 May 2014 |
Time: |
14:00 |
Inspection No.: |
26 |
|
Nil |
|
|
|
Follow-up
Observations |
1. |
Muddy water has
been cleared (Closed). |
2. |
Chemical containers
have been removed (Closed). |
|
New
Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
27 May 2014 |
Time: |
14:00 |
Inspection No.: |
27 |
|
Nil |
|
|
|
Follow-up
Observations |
|
Nil. |
|
|
|
New
Observations |
1. |
Muddy water was
observed in the U-channel next to the construction site. Muddy water was also
observed on the road leading to the construction site. The Contractor
should review measures to prevent silt and debris from depositing in drainage
systems and clear the muddy water in the U-channel and public road. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |