Appendix
L
Statistics
on Complaints, Notifications of Summons and Successful Prosecutions
|
Date
Received
|
Subject
|
Status
|
Total
no. followed up by the ET this month
|
Total
no. followed up by the ET since project commencement
|
Environmental
complaints
|
19 December 2013
|
EPD referred a complaint from Lot no. 116 of Fui Sha Wai at
Tai Hang of Tai Po which is concerned about the construction noise and
diesel-like smell generated from construction activities nearby which caused
nuisance and health problems on 19 December 2013 morning.
|
Closed
|
0
|
4
|
24 February 2014
|
EPD referred an air-and-odour
complaint on 24 February 2014. The complainant complained about the construction
site located near the bus stop in Fui Sha Wai, Tai Hang, Tai Wo Service Road West. When construction works were
carried out, odour, white smoke and dust were
generated. The complainant asked for follow-up actions.
|
Closed
|
|||
23 October 2014
|
EPD referred an air complaint on 24 October
2014. A resident complained against the
excavation works of Tai Wo Service Road West
between Nam Wah Po & Tai Hang Tsuen, which have
piled up high stockpiles, causing serious dust nuisance to his house. The resident also complained that the stockpiles
have not been covered and watered properly. He now requires the EPD to follow
up. The location of complaint is near Lamppost
Location EB5717. |
Closed
|
|||
31 December 2014
|
EPD referred a water complaint on 31
December 2014. The complainant complained about the muddy
river outside Tai Hang Village Office on 29 December 2014. It was suspected
that the muddy water was discharged from the construction works of the
Project. He required the EPD to follow up. |
Closed
|
|||
Notification
of summons
|
-
|
-
|
-
|
0
|
0
|
Successful
Prosecutions
|
-
|
-
|
-
|
0
|
0
|